Hiệu suất công nghệ khoan kích ngầm định hướng đặt đường ống

Hiệu suất công nghệ khoan kích ngầm định hướng đặt đường ống. Pipe-Jacking Project Performance. Similar Project Performance & Financial Report of CHEC. Dịch vụ thi công khoan ngầm - Minh Phuong Corp.

Hiệu suất công nghệ khoan kích ngầm định hướng đặt đường ống

Pipe-Jacking Project Performance.  Similar Project Performance & Financial Report of CHEC

TABLE OF CONTENTS
1.    Pipe-Jacking Project Performance of CHEC    4
2.    Financial report of CHEC    5

1.    PIPE-JACKING PROJECT PERFORMANCE OF CHEC

-    Lot 3.2 Pipe-jacking Work of Shanghai Combined Sewage Control Project, China
-    Samutprakarn Wastewater Management in Thailand
-    Pipe-jacking Work of Ho Chi Minh City Enviroment Improvement Project, Vietnam
-    D43 – Supply, Lay, Testing and Commissioning of Sewerage Pipeline Kuala Lumpur, Malaysia
-    Attach other pipe-jacking performance

Pipe Jacking Project Performance

Pipe-Jacking Project Performance

-    Lot 3.2 Pipe-jacking Work of Shanghai Combined Sewage Control Project, China

Pipe Jacking

Hiệu suất công nghệ khoan kích ngầm định hướng đặt đường ống

EMPLOYER:Shanghai Combined Sewage Treatment Construction Company
CONTRACTOR:China Harbour Engineering Company Ltd PERIOD:1990.03—1992.04
CONTRACT VALUE:38.58Million CNY

Pipe-jacking Work of Shanghai Combined Sewage Control Project

Pipe Jacking Project Performance
Công nghệ khoan kích ngầm định hướng đặt đường ống

- Lot 3.2 Pipe-jacking Work of Shanghai Combined Sewage Control Project, China
Brief Introduction
Three breakthroughs and one series in pipe-jacking technology have been achieved in Lot 3.2 Pipe-jacking Work of Shanghai Combined Sewage Control Project: maximum inside diameter 3,500mm, once pipe-jacking length 1,275m, underground curved jacking available, and forming the pipe-jacking technology for diameter 2000~3500mm pipes.

-    Samutprakarn Wastewater Management in Thailand

Samutprakarn Wastewater Management in Thailand

EMPLOYER: Pollution Control Department of Thailand CONTRACTOR: NVPSKG & CHEC JV.
PERIOD: 1999.02-2003.08
CONTRACT VALUE: 515 Million Baht

Pollution Control Department of Thailand

Công nghệ khoan kích ngầm định hướng đặt đường ống ngầm

-    Samutprakarn Wastewater Management in Thailand
Brief Introduction
Samutprakarn Wastewater Management Project (SPWWMP) is designed to be able to treat community and industrial wastewater collected from the most densely populated areas of the province. It will be laid by tunneling and pipe jacking under roadways. Wastewater flows generated on the west bank of Chao Praya river will be transfer to the east bank through tunnels under the river and combined the water from the east bank areas. Then the combined flow will be piped to treatment plant.
After the treatment process, treated wastewater will be released through a 3.4- km outfall pipe into the Gulf of Thailand. The CETP will have the capacity to treat up to 525,000 cubic meters of wastewater a day.

Pipe-Jacking Project Performance
-  Pipe-jacking Work of Ho Chi Minh City Enviroment Improvement Project, Vietnam

Pipe-jacking Work of Ho Chi Minh City Enviroment Improvement Project

Công nghệ khoan kích ngầm

EMPLOYER: PMU
CONTRACTOR: China Harbour Engineering Company Ltd PERIOD: 2003.10—2006.10
CONTRACT VALUE: 29,200,000 USD (World Bank Finance)
KEY FEATURES: Approximately 11 kilometers long

DN3000 TBM

DN3000 TBM 

Pipe Jacking

Pipe Jacking

Pipe-Jacking Project Performance
-    Pipe-jacking Work of Ho Chi Minh City Enviroment Improvement Project, Vietnam
Brief Introduction
The work is a canal improvement work of Ho Chi Minh City. It's composed in the fulllength of about 9,100m pull pipes with diameter 3m; 18 operating pits with diameter 9m, depth 22m; 18 accepting pits with diameter 7m, depth 22m; wherein depth of two NLTN pits and east bank pits is about 42m; grooved embedded pipes about 8,016m with pipe diameterranging from 200mm to 2,000mm; as well as 56 overflow wells and 205 manholes.

-    D43 – Supply, Lay, Testing and Commissioning of Sewerage Pipeline Kuala Lumpur, Malaysia

Thi công khoan ngầm

Thi công khoan kích ngầm

EMPLOYER: PMU
CONTRACTOR: China Harbour Engineering Company Ltd. PERIOD: 2014.07—2019.03
CONTRACT VALUE: 107.4 MYR

-    D43 – Supply, Lay, Testing and Commissioning of Sewerage Pipeline Kuala Lumpur, Malaysia
Brief Introduction
The project is located in Kepong District, Kuala Lumpur, and mainly includes the construction of a sewage pipe network with a length of about 21.6 kilometers. The diameter of the gravity gravity pipe jacking pipe in this tender section is 375mm, 450mm, 525mm, 900mm, 1050mm, 1200mm, 1500mm and other diameters.
Notable features:
Mainly for small diameter pipe jacking. It is a difficult point in pipe jacking engineering, especially small-diameter rock pipe jacking.
The first application of the glazed clay pipe jacking, there is no domestic application precedent.
There is no domestic application precedent for the auger pipe jacking construction technology.

-    Attach other pipe-jacking perfprmance

Attach other pipe-jacking perfprmance

See details: Vietnam Vung Ang Power Plant Phase II Pipe Jacking Project

 

CÔNG TY CP TƯ VẤN ĐẦU TƯ & THIẾT KẾ XÂY DỰNG MINH PHƯƠNG

Địa chỉ: Số 28B Mai Thị Lựu, Phường Đa Kao, Q.1, TPHCM

Hotline:  0903649782 - (028) 3514 6426

Email: nguyenthanhmp156@gmail.com

 


Tin tức liên quan

VẬT LIỆU, CÔNG NGHỆ, CÁCH LẮP ĐẶT ĐƯỜNG ỐNG CÁCH NHIỆT NGẦM
VẬT LIỆU, CÔNG NGHỆ, CÁCH LẮP ĐẶT ĐƯỜNG ỐNG CÁCH NHIỆT NGẦM

1381 Lượt xem

Vật liệu, công nghệ, phương pháp lắp đặt đường ống cách nhiệt ngầm phụ thuộc vào điều kiện địa phương của công trình - mục đích, yêu cầu thẩm mỹ, sự hiện diện của các nút giao thông phức tạp với kết cấu và thông tin liên lạc, loại đất - và cần được thực hiện trên cơ sở tính toán kinh tế kỹ thuật của các phương án khả thi.

Kỹ thuật khoan kéo ống ngầm thực hiện thi công lắp đặt ống qua đường
Kỹ thuật khoan kéo ống ngầm thực hiện thi công lắp đặt ống qua đường

1148 Lượt xem

Kỹ thuật khoan kéo ống ngầm thực hiện thi công lắp đặt ống qua đường, qua sông bằng công nghệ khoan robot thực hiện bởi nhà thầu lắp đặt công trình ngầm

Kỹ thuật khoan ngầm kéo ống dẫn nước thải qua khu dân cư
Kỹ thuật khoan ngầm kéo ống dẫn nước thải qua khu dân cư

1334 Lượt xem

Không được đào hoặc đóng đường, đường ống dẫn nước thải chính của chung cư B1 số 2 Trường sa phải "khoan" qua đường bằng kỹ thuật khoan ngầm kéo ống dẫn nước thải qua khu dân cư.

Có nên lựa chọn công nghệ khoan định hướng hay không? Đơn giá khoan ngầm bao nhiêu?
Có nên lựa chọn công nghệ khoan định hướng hay không? Đơn giá khoan ngầm bao nhiêu?

1286 Lượt xem

Mặc dù đây không phải là một nhiệm vụ phức tạp, nhưng việc phạm sai lầm có thể dẫn đến nhiều thiệt hại và do đó, bạn có thể gặp rắc rối. Vậy có nên lựa chọn công nghệ khoan định hướng hay không? Đơn giá khoan ngầm bao nhiêu? Chúng ta hãy cùng nhau tìm hiểu ngay sau đây:

Rủi ro trong quá trình kéo ống của khoan định hướng ngang
Rủi ro trong quá trình kéo ống của khoan định hướng ngang

1497 Lượt xem

Sự thành công của khoan định hướng ngang (HDD) phần lớn phụ thuộc vào sự thành công của hoạt động kéo lùi, khi ống sản phẩm được lắp đặt trong lỗ khoan đã tạo.

Kỹ thuật vận hành máy khoan kéo ống ngầm bằng phương tiện khoan robot
Kỹ thuật vận hành máy khoan kéo ống ngầm bằng phương tiện khoan robot

1354 Lượt xem

Kỹ thuật vận hành máy khoan kéo ống ngầm bằng phương tiện khoan robot


Bình luận
  • Đánh giá của bạn
Đã thêm vào giỏ hàng