CONSTRUCTION MEASURES OF SURROUND DRILLING 04 CW DN2600 PIPELINES

Drilling underground jacking 04 lines of reinforced steel pipes DN2800 and pulling construction of 04 lines of CW DN2600 pipelines.

CONSTRUCTION MEASURES OF SURROUND DRILLING 04 CW DN2600 PIPELINES

 

TABLE OF CONTENTS

1.         GENERAL INTRODUCTION   3

1.1.      PROJECT OVERVIEW    3

1.2.      DOCUMENTATION PURPOSE   3

1.3.      LEGAL DOCUMENTS  3

1.4.      DEFINITIONS AND Acronyms  3

2.         PREPARATION OF CONSTRUCTION   4

3.         CONSTRUCTION HUMAN RESOURCES  4

4.         CONSTRUCTION EQUIPMENT   5

5.         TEMPORARY WORKS FOR CONSTRUCTION   6

6.         DRILLING CONSTRUCTION PROGRESS  7

7.         CONSTRUCTION MATERIALS  7

8.         DEVELOPMENT, DISTANCE TO US SURFACE CONSTRUCTIONS    7

9.         CONSTRUCTION METHODS  7

9.1.      SURVEY   7

9.2.      MOBILE MACHINERY, EQUIPMENT AND HUMAN RESOURCES  8

9.3.      ROAD SURFACE OF DRILLING AREA   8

9.4.      PREPARATION OF DRILLING WORK   8

9.8.      CW DN2600 TUBE PULLING WORK   12

9.9.      CLEANING AND REFUNDING WORK   14

10.       MEASURES Environmental sanitation, fire prevention and SITE SECURITY

10.1.   GENERAL RULES  14

10.2.   SECURUTY15

10.3.   ENVIRONMENTAL SANITATION   15

10.4.   FIRE FIGHTING, INTERNAL TRAFFIC SAFETY   15

10.5.   WORKER SAFETY   17

 

CONSTRUCTION MEASURES OF SURROUND DRILLING 04 CW DN2600 PIPELINES

 

1. GENERAL INTRODUCTION

1.1 PROJECT OVERVIEW

Name of the project: Drilling underground jacking 04 lines of reinforced steel pipes DN2800 and pulling construction of 04 lines of CW DN2600 pipelines.

Belonging to the project: Vung Ang II Thermal Power Plant

Type of project, grade of work: Group B projects, Water pipeline works, Grade II.

Location: Ky Anh district, Ha Tinh province.

1.2 DOCUMENTATION PURPOSE

The purpose of this document is to provide a method for the Contractor to implement and control the construction of 4 underground CW DN2600 pipelines across the road.

1.3 LEGAL DOCUMENTS

Construction Law No. 50/2014/QH 13 dated June 18, 2014 of the 13th National Assembly, 7th session;

Law on Environmental Protection No. 72/2020/QH14 passed on January 17, 2020 by the 14th National Assembly;

Decree No. 15/2021/ND-CP dated March 3, 2021 of the Government detailing a number of contents on construction investment project management;

Decree No. 06/2021/ND-CP dated January 26, 2021 of the Government detailing a number of contents on quality management, construction and maintenance of construction works;

Decree No. 11/2010/ND-CP dated February 24, 2010 of the Government providing for the management and protection of road traffic infrastructure;

Circular No. 50/2015/TT-BGTVT dated September 23, 2015 of the Ministry of Transport on "Guiding the implementation of a number of articles of Decree No. 11/2010/ND-CP dated February 24, 2010.

1.4 DEFINITIONS AND ACRONYMS

Investor

Vung Ang II Thermal Power Company Limited

Project

Vung Ang II Thermal Power Plant

Contractors

DHI-SCT . Joint Venture

Package

Design, Fabrication and Construction, Installation

            HSE                :           Health, Safety and Environment

            BDA               :           Project department

            CBAT             :           Safety Officer

            CBKT             :           Technical staff

            MMTB           :           Devices

            HT                   :           System

2. PREPARATION OF CONSTRUCTION

The preparation work has been carried out according to the construction item of the whole pipeline.

3. CONSTRUCTION HUMAN RESOURCES

List of personnel participating in underground drilling

No.

First and last name

Date of birth

Identity card number

Home town

Work

1

Nguyen Van Thanh

6/5/1970

038070006601

Thanh Hoa

Director

2

Tran Anh Tuan

13/06/1972

273136899

Ha Tinh

Deputy commander

3

Đang Xuan Dien

7/10/1961

024716077

Nghe An

Deputy commander

4

Đang Minh Nhut

1986

025748413

Đong Thap

Deputy commander

5

Đo Thi Kim My

17/05/1997

291141831

Tay Ninh

Secretary

6

Nguyen Ngoc Thanh

20/03/1992

173754257

Thanh Hoa

Captain

7

Nguyen Tien Long

27/06/1998

175023765

Thanh Hoa

Technical staff

8

Tran Manh Sung

30/09/1976

033076001982

Hung Yen

Drilling machine driver

9

Au Le Hai

1973

312381178

Bac Giang

Drilling machine driver

10

Duong Van Minh

19/04/1987

281286071

Nghe An

Drilling Assistant

11

Nguyen Thanh Hung

03/09/1972

038072003565

Thanh Hoa

Drilling Assistant

12

Nguyen Van Sang

12/081968

261623922

Thai Nguyen

Drilling Assistant

13

Vo Xuan Oanh

30/10/1965

181484282

Nghe An

Drilling Assistant

14

Đoan Van Dong

1/12/1996

251064894

Lam Đong

Drilling Assistant

15

Duong Van Dai

10/10/1999

187766885

Nghe An

Drilling Assistant

16

Nguyen Ngoc Noi

20/11/1970

172156753

Thanh Hoa

Drilling Assistant

17

Phan Van Truc

20/03/1977

261221690

Thai Nguyen

Drilling Assistant

18

Pham Minh Tuan

19/05/1976

320940871

Ben Tre

Technical staff

19

Đao Minh Tuan

29/08/1995

362427232

Can Tho

Technical staff

20

Nguyen Minh Phung

09/08/1995

301600511

Long An

Technical staff

4. CONSTRUCTION EQUIPMENT

List of construction machinery and equipment:

No.

Types of machinery and equipment

Amount

Own/Rent

Note

1

Crane 50 tons

01

2

Generator 20 kVA

01

3

Excavator 1 m3

02

4

Welding machine A300

5

5

Grinding and cutting machine Ø150

4

6

Oil air compressor (8m3/min)

01

7

Hand drill

04

8

Hole Drilling Machine

01

9

Pressure Compressor + Recorder

01

10

HDD underground pipe drilling machine

01

GS-700 -LS

11

Drilling fluid mixer 2000L

01

12

Drill head locator

01

13

Laser distance meter

01

14

Depth gauge

01

15

walkie talkie

03

16

Tank truck carrying clean water

01

17

Concrete tank truck

01

18

Ground-penetrating radar detector

01

19

Guide drill rod

20

20

Drill head and extension shallow drill head

07

21

Hoist 5-10 tons

01

22

Mother of pearl / lotus leaf pile driving machine

01

Technical parameters of drilling machine GS - 700 – LS:

No

Parameters

Value

1

Thrust force

700KN

2

Traction

1400KN

3

Torque

30000Nm

4

Engine power

199KW

5

Max drill diameter

1500mm

6

Maximum drilling length

900m

5. TEMPORARY WORKS FOR CONSTRUCTION

Minh Phuong will transport 01 10 ft container containing equipment, construction tools and other works located at the gathering yard in the construction area.

Office at the construction site:

Housing of officials/workers will be rented houses in construction areas about 6 km.

Use 20kVA generator power supply to weld pipes. Water source for drilling is provided by tank trucks and mobile water tanks.

6. DRILLING CONSTRUCTION PROGRESS

Construction progress is calculated from the date the Investor receives the construction approval permit.

7. CONSTRUCTION MATERIALS

The list of main materials for construction of 04 sections of underground pipelines across the road, each 39m long pipeline section includes the following:

No

Materials and equipment

Std

Facing

Sch

inch

Unit

Amount

1

CW pipe DN2600

BE

40

m

156

2

DN2800 reinforced steel pipe

m

156

8. DEVELOPMENT, DISTANCE TO US SURFACE CONSTRUCTIONS

The depth of burying pipes when crossing the road is determined based on API RP 1102, the input parameters are the wall thickness of the pipe, the depth of burying the pipe through the road, the parameters of the road and the operating vehicle. Test the stress in the pipe against the allowable stress and the fatigue of the weld against the fatigue limit of the weld to ensure that the pipe is not damaged or destroyed during operation.

9. CONSTRUCTION METHODS  

9.1 SURVEY

Survey of construction layout

The construction team, the survey team discussed and calculated the actual characteristics of the ground, the existing obstacles if any (lines, underground cables, sewer pipes, ...), determined the location of drilling machines, welding nests. Combination of CW DN2600 pipe and welding of reinforced steel pipe, preparation for pulling, construction plan, gathering equipment and materials, possible obstacles and proposing solutions to speed up progress (if necessary).

Thus, it can be seen that the difficulties mainly stem from natural conditions: ground, geographical location, weather. To overcome these difficulties and speed up the progress, the contractor determined to follow the following criteria:

Optimal resource mobilization for all stages.

Reasonable arrangement of resources to coordinate smoothly between construction sites, with local authorities, functional agencies and the Investor without creating downtime during the construction process.

Strictly control, find potential risks, focus on handling immediately to prevent these potentials from developing into problems.

9.2 MOBILE MACHINERY, EQUIPMENT AND HUMAN RESOURCES

Based on survey data, Minh Phuong has selected suitable equipment and materials to gather to the project. The correct and sufficient selection ensures efficient construction, on schedule and minimizes the costs incurred.

Construction personnel to carry out the project must ensure that they have been trained in safety and have specialized certificates appropriate to the field in charge.

9.3 ROAD SURFACE OF DRILLING AREA

When starting underground drilling through the road, the construction unit will install a speed limit sign of 5 km/h.

Reinforce the roadbed by spreading 10mm thick steel plates on the road surface at the underground drilling site.

Appoint people to be on duty 24/24 h at the construction site to remind vehicles to limit speed when passing through the construction area.

The borehole is filled with betonite, after pulling the pipe, it is filled with low grade concrete or soil cement concrete to compensate for the empty hole in the pipe drilling process.

After pulling the pipe, the borehole part is reinforced with low grade concrete or soil cement concrete, which is fixed and kept stable after 72 hours before removing the reinforced corrugated iron layer on the road surface.

9.4 PREPARATION OF DRILLING WORK

Using an electronic total station to determine the scope of the construction site in the field.

Build 04 2600mm diameter pipelines, can change the number of pipes with 2 pipes (DN3700) at the detailed engineer stage.

Build 04 2600mm diameter pipelines

Barriers, construction site signs

10. SURFACE DRILLING STAINLESS STEEL PIPE REINFORCED DN2800

High power hydraulic jacks are used to push special pipe joints into the ground with front mounted locomotives.

The construction of the drainage system by underground jacking technology is carried out through the following steps:

1.  Survey the condition and condition of the ground before construction and measure and determine the construction location.

2.    Construction of jacking wells and receiving wells.

- Jacking well: In order to be able to execute underground jacking drills and install pipes with a depth of 9.0m compared to the road surface, the minimum depth of construction pits is 9.5m deep. Dimensions of the excavated hole are: length=3.0m; width = 3.0m; depth=9.5m. The jack drill is placed at a height of +0m above the bottom of the jacking well. The jacking well is reinforced with Larsen piles to prevent landslides during the construction process.

- Receiving well: dug to a depth of 9.5m above the road surface. This well has the effect of opening the borehole, receiving the pipe and constructing the pipe winch to help orient the pipe. The cross-section of the receiving pit has the following area: length=3.0m; width = 3m; depth=9.5m. The well received reinforcement of Larsen piles to prevent landslides for the receiving well during the construction process.

3.    Precise positioning of soft eye position at jack-well outlet and receiving-well inlet.

- Soft eye positioning is based on the design elevation of the bottom of the culvert.

4.    Transporting construction equipment and tributes to the construction site.

-   The sluice gates have a different structure from the open excavation culverts to be suitable for pipe jacking. There are 3 types of tributes:

+   Standard pipe: This culvert has a normal structure, only the position of a crane hook is used to lower the drain into the size of the pipe.

+   Grouting pipe (Grouting pipe): This sluice has the same structure as a regular culvert but has 3 additional holes located 120o apart along the circumference of the culvert to serve the pumping of Bentonite grout around the culvert wall.

+    Intermediate pipe: This is a pair of drains including male pipe (Male pipe) and female pipe (Female pipe). The intermediate jack is arranged between these two drains. After jacking the entire sewer line, the intermediate jack is dismantled and pushed together.

5.    Installation of ground support equipment for jacking: Crane truck, sludge settling tank, dredger, generator, Bentonite pumping station.

- Bentonite pumping station has the purpose of pumping Bentonite mortar to the outside around the pipe body to reduce the friction between the soil and the pipe wall.

6.    Installation of supporting equipment in the well for jacking: Mud pump system, ventilation system, control system, hydraulic system, electrical system, bentonite pumping system, laser guidance system , gasket to prevent water, jet wall.

7.    Install the main jacking system and connect with supporting devices: Hydraulic jack, push jack ring: contact washer between drain and main jack, drill head, intermediate jack (if any).

8.    Operate the jacking system to bring the drill head into the ground to start the pipe jacking work. Install successive culverts behind the drill head and intermediate jacking stations (if necessary) until the culvert and drill head enter the receiving well.

-    During the pipe jacking process, it is necessary to monitor the main jacking force. If the main jacking force is too large, it can burst the drain, then it is necessary to install intermediate jacking stations to reduce the main jacking force.

 -    The positions of intermediate jacking stations are determined based on calculations.

9.    At the location of the receiving well, install the receiving gasket, the jack receiving frame.

10.  Transport the drill head and jacking aids in the tunnel out of the receiving well. Clean the construction site according to regulations.

Drilling technology

Drilling technology

Drilling fluid used for pipe pulling work

Drilling fluid is an important component of successful pipe pulling. Basically, drilling fluid is a mixture of water, bentonite and additives. The amount of bentonite used is calculated based on the engineering geological parameters and the diameter and length of the borehole.

Drilling fluid has the following functions: 

Breaking, mixing soil, rock, sand in the tunnel where the drill head and break head pass when being pumped and compressed with high pressure.

Establish and maintain tunnel stability (avoid tunnel collapse).

Lubricate the drill head, break head and drill rod, reducing heat concentration on these tools.

Transporting soil, rock, sand in the tunnel to the outside.

Another important property of drilling fluid is that it can be reused through the use of recycling equipment.

 

Xem thêm BIỆN PHÁP THI CÔNG KHOAN NGẦM 04 TUYẾN ỐNG CW DN2600 >>

 

 

CÔNG TY CP TƯ VẤN ĐẦU TƯ & THIẾT KẾ XÂY DỰNG MINH PHƯƠNG

Địa chỉ: Số 28B Mai Thị Lựu, Phường Đa Kao, Q.1, TPHCM

Hotline:  0903649782 - (028) 3514 6426

Email: nguyenthanhmp156@gmail.com

 


Tin tức liên quan

Công nghệ khoan định hướng HDD
Công nghệ khoan định hướng HDD

1094 Lượt xem

Bài viết này là để phân tích ngắn gọn công nghệ khoan định hướng HDD, và thông qua Công ty CP Tư vấn đầu tư và Thiết kế xây dựng Minh Phương trong Dự án khoan định hướng ngang và tổng kết trao đổi kinh nghiệm xây dựng.

Hợp đồng giao khoán thi công khoan qua đường bằng robot
Hợp đồng giao khoán thi công khoan qua đường bằng robot

1113 Lượt xem

Hai bên nhất trí ký kết hợp đồng giao khoán thi công khoan qua đường bằng robot đặt ống sắt D560mm này với các điều khoản sau:

Kỹ thuật khoan ngầm kéo ống dẫn nước thải qua khu dân cư
Kỹ thuật khoan ngầm kéo ống dẫn nước thải qua khu dân cư

1175 Lượt xem

Không được đào hoặc đóng đường, đường ống dẫn nước thải chính của chung cư B1 số 2 Trường sa phải "khoan" qua đường bằng kỹ thuật khoan ngầm kéo ống dẫn nước thải qua khu dân cư.

Công nghệ khoan ngang qua đường lắp đặt đường ống ngầm HDD
Công nghệ khoan ngang qua đường lắp đặt đường ống ngầm HDD

2312 Lượt xem

Công nghệ khoan ngang qua đường lắp đặt đường ống ngầm HDD đã trở nên “tương thích với đá” hơn 10 năm trước, các phương pháp đã được cải tiến liên tục, cũng trở nên đa dạng hơn và việc xây dựng đường ống trong đá đã trở thành thông lệ từ một chuyên ngành.

Khoan đặt ống ngầm vượt sông
Khoan đặt ống ngầm vượt sông

1745 Lượt xem

Phương pháp khoan đặt ống ngầm vượt sông này rút ngắn thời gian xây dựng đoạn băng qua sông, đặc biệt là trong trường hợp băng qua sông, vì công việc có thể được thực hiện quanh năm, chúng không liên quan đến bất kỳ thời gian đóng băng, băng trôi, sụt giảm hoặc dâng cao. trong mực nước.

Mũi khoan phù hợp cho các điều kiện nền đất mềm, trung bình và cứng
Mũi khoan phù hợp cho các điều kiện nền đất mềm, trung bình và cứng

1443 Lượt xem

Tùy thuộc vào đặc tính của đất, sự phân loại của đất phụ thuộc vào một số đặc tính kỹ thuật, chẳng hạn như cường độ nén, khả năng chịu lực, kết quả thử nghiệm xuyên tiêu chuẩn (SPT) và cường độ cắt mà lựa chọn mũi khoan phù hợp cho các điều kiện nền đất mềm, trung bình và cứng.


Bình luận
  • Đánh giá của bạn
Đã thêm vào giỏ hàng