Schedule of CW Pipe Underpass VA1 Facility

 Schedule of CW Pipe Underpass VA1 Facility (80m), Construction work start April 1st, 2023. Mẫu phân công lịch trình công trình thi công khoan ống ngầm cho nhiều giai đoạn.

Schedule of CW Pipe Underpass VA1 Facility (80m)

Schedule of CW Pipe Underpass VA1 Facility (80m), Construction work start April 1st, 2023. Mẫu phân công lịch trình công trình thi công khoan ống ngầm cho nhiều giai đoạn.

Construction work start April 1st, 2023

Mẫu lịch trịch cho phân công công trình xây dựng

Schedule of CW Pipe Underpass VA1 Facility

- Start temporary work 1st Dec. 2022

- No.5 : Jet gouting, excavation work for Launch Shaft, Receiving Shaft within 90days

- Start site construction work 1st April. 2023

- No.8 : Concrete wall, slab at Launch Shaft, Receiving Shaft, install TBM machine 30days

- No.9 ~ No.12 : TBM work for each 80m, 40days

- No.13 : Preparation of GRP Pipe installation 30days

- No.14 ~ No.17 : GRP install and joint work for each 80m, 60days (15 joint, 4days/joint)

- No.18 : Grouting between con'c pipe & GRP pipe for 80m, 20days

- No.19 : Backfill by sand and concrete block for Launch Shaft, Receiving Shaft 60days

- No.20 : concrete slab for outside Launch Shaft, Receiving Shaft and joint at T.P 30days

- No.21 : Hand over civil work and mach.work 20day

See Details: Hiệu suất công nghệ khoan kích ngầm định hướng đặt đường ống

Minh Phương Corp là Đơn vị

- Tư vấn lập dự án xin chủ trương

- Tư vấn dự án đầu tư

- Tư vấn lập dự án kêu gọi đầu tư

- Lập và đánh giá sơ bộ ĐTM cho dự án

- Thiết kế quy hoạch chi tiết tỷ lệ 1/500

- Thi công Dự án Khoan ngầm

- Biện pháp thi công khoan ống ngầm 

- Viết Hồ sơ Môi trường.

+ Giấy phép Môi trường.

+ Báo cáo Công tác bảo vệ Môi trường.

+ Báo cáo Đánh giá tác động Môi trường ĐTM.

Tại sao nên chọn Công ty CP Tư vấn Đầu tư & Thiết kế Xây dựng Minh Phương ?

Công ty được hình thành trên cơ sở sáng lập viên từng là giám đốc dự án, kỹ sư chuyên ngành xây dựng, công nghệ kỹ thuật, quản trị kinh doanh, từng điều hành các tập đoàn lớn, các Công ty Liên doanh nước ngoài hàng chục năm.

Với đội ngũ nhân viên đầy nhiệt huyết, năng lực, và giàu kinh nghiệm.

Là Đơn vị chuyên tư vấn và nhận thầu các dự án đầu tư và thiết kế xây dựng trên Toàn Quốc.

Tư vấn nhiệt tình, giá cả hợp lí, mang tính cạnh tranh cao.

Quy trình làm việc đảm bảo tiến độ nhanh chóng, hiệu quả cao nhất:

Chất lượng dịch vụ được khách hàng tin tưởng và ưu tiên đặt khách hàng lên hàng đầu.

Triển khai thực hiện ngay khi khách hàng kí hợp đồng.

Đảm bảo đúng tiến độ hoàn thành dự án.

MỌI CHI TIẾT XIN LIÊN HỆ: 0903 649 782

Hoặc gửi về email: nguyenthanhmp156@gmail.com

 

CÔNG TY CP TƯ VẤN ĐẦU TƯ & THIẾT KẾ XÂY DỰNG MINH PHƯƠNG

Địa chỉ: Số 28B Mai Thị Lựu, Phường Đa Kao, Q.1, TPHCM

Hotline:  0903649782 - (028) 3514 6426

Email: nguyenthanhmp156@gmail.com

 


Tin tức liên quan

Construction method for HDD drilling across roads and canals
Construction method for HDD drilling across roads and canals

305 Lượt xem

The purpose of this document is to provide the methodology for the Contractor to execute and control the HDD drilling works across roads and canals, and the pulling of 16” steel pipes inside 20” steel casing pipes, under the Project “Fuel Pipeline System for Aircraft from the Upstream Port to Long Thanh International Airport.”

Horizontal Directional Drilling (HDD) Process for Gas Pipeline Project
Horizontal Directional Drilling (HDD) Process for Gas Pipeline Project

878 Lượt xem

This purpose of this document is to describe in general terms the HDD process and methodologies that will be utilized for “Approximately 94 km of 30-inch onshore pipeline from An Minh Landfall Station to O Mon Gas Distribution Center (GDC) at Can Tho Province” section this project.

Execution plan  for horizontal directional drilling gas pipeline project
Execution plan for horizontal directional drilling gas pipeline project

787 Lượt xem

Execution plan  for horizontal directional drilling gas pipeline project. This execution plan is proposed according to the work list which is provided by EPC as well as all the HDD geological condition are considered as the normal soil, and the HDD list is as followed.

Construction Method for Horizontal Directional Drilling (HDD) of the Gas Pipeline
Construction Method for Horizontal Directional Drilling (HDD) of the Gas Pipeline

769 Lượt xem

Construction Method for Horizontal Directional Drilling (HDD) of the Gas Pipeline. Present the horizontal directional drilling method for the project, general construction organization methods, on-site construction organization, construction site layout, quality control measures, applicable technical standards, and construction sequence.

Explanatory report on construction methods for horizontal directional drilling (HDD)
Explanatory report on construction methods for horizontal directional drilling (HDD)

1010 Lượt xem

The purpose of this document is to propose a method for the Project Management Consultant and the Investor to review and approve for the Contractor to execute and control the drilling process for pulling a steel pipe with a diameter of D200 under the road.

Horizontal Directional Drilling (HDD) Method Statement
Horizontal Directional Drilling (HDD) Method Statement

3608 Lượt xem

This document has been prepared to describe the methodology by which MCD/HDDT propose undertaking the site preparation, mobilization, drilling operations, pipe installation, pre-commissioning and reinstatement operations for the installation of the 6 HDD crossings on the Block B Omon Project - Onshore Pipeline.


Bình luận
  • Đánh giá của bạn
Đã thêm vào giỏ hàng