METHOD STATEMENT FOR CW PINELINE UNDERPASS VA1 FACILITY

Biện pháp thi công khoan ống CW VA1. METHOD STATEMENT FOR CW PINELINE UNDERPASS VA1 FACILITY. Method Statement For Cw Pineline Underpass VA1 Facility VA2-DD09-P0ZEN-720019

METHOD STATEMENT FOR CW PINELINE UNDERPASS VA1 FACILITY

Method Statement For Cw Pineline Underpass VA1 Facility VA2-DD09-P0ZEN-720019

Biện pháp thi công khoan ống CW VA1 bằng tiếng anh.

TABLE OF CONTENTS

1. INTRODUCTION....................................................................................................................... 4

1.1 General Introduction ............................................................................................................... 4

1.2 Abbriation and difinitions ....................................................................................................... 4

1.3 Scope of work .......................................................................................................................... 5

1.4 Construction Period................................................................................................................. 6

2. General condition and method statement................................................................................. 6

2.1 General Introduction ............................................................................................................... 6

2.2 Ground Conditions.................................................................................................................. 7

2.3 Launch Shaft and Receiving Shaft.......................................................................................... 8

2.4 Jacking Pipes......................................................................................................................... 11

3. Construction METHOD STATEMENT................................................................................. 11
3.1 Shaft construction.................................................................................................................. 11

3.1.1 Construction sequence.................................................................................................... 11
3.1.2 Sheet pile construction................................................................................................... 12
3.1.3 Jet Grouting construction ...............................................................................................15
3.1.4 Excavation work and strut installation........................................................................... 19
3.2 Jacking Pipe........................................................................................................................... 21

3.2.1 RCJP Supply................................................................................................................... 21
3.2.2 Soil improvement underneath the box culvert ...............................................................23
3.2.3 Sequence......................................................................................................................... 24
3.2.4 Pipe jacking preparation................................................................................................. 25
3.2.5 Cutting soft-eye at Launching shaft ............................................................................... 26
3.2.6 Testing and initial excavation......................................................................................... 27
3.2.7 Pipe jacking progress...................................................................................................... 27
3.2.8 Inside pipe surveying...................................................................................................... 28
3.2.9 Slurry mixing.................................................................................................................. 29
3.2.10 Cutting soft-eye at Arriving shaft................................................................................. 29
3.2.11 Pipe jacking machine recovery..................................................................................... 30
4. Safety measure of pipe-JACKING method............................................................................. 30

4.1.1 Safety Measure............................................................................................................... 31
5. GRP installation (bY MAINCON)........................................................................................... 31

Method Statement For Cw Pineline Underpass VA1 Facility VA2-DD09-P0ZEN-720019

Method statement for CW pineline underpass VA1 Facility

1. INTRODUCTION

1.1    General Introduction

The Vung Ang II thermal power plant is part of the Vung Ang thermal power center and is the second complex of the coal-fired electricity generating plant located in the Vung Ang industrial zone, Ky Loi commune, Ky Anh district, Ha Tinh province in Vietnam. Vung Ang II will be constructed adjacent to Vung Ang I which is already in operation. It consists of two turbines with a total capacity of 1,200 MW. Both will be fueled by imported anthracite, hard coal.

Construction Site Condition

Fig1.1 Construction Site Condition

1.2    Abbreviation and definition
The Owner                                       Vung Ang II Thermal Power LLC

The Contractor                                 DHI-SCT Joint Venture

HSE                                                  Health, Safety and Environment
MS                                                    Method Statement

RA                                                    Risk Assessment

PPE                                                   Personal Protective Equipment
QA/QC                                             Quality Assurance/Quality Control

CW                                                   Cooling Water

VA1                                                  Vung Ang 1

RCJP                                                 Reinforcement Concrete Jacking Pipe

1.3    Scope of work

To install 4 pipelines with Diameter 2600mm CW pipeline underground of Vung Ang 2 Thermal Power Plant at crossing area with Vung Ang 1 conveyor-belt by pipe jacking method.

Plan View of Construction Location

Fig.1.2 Plan View of Construction Location

Section View of CW pipeline

Fig.1.3 Section View of CW pipeline(4×DN2600GRP)

The characters of GRP are as below.
Method Statement For Cw Pineline Underpass VA1 Facility VA2-DD09-P0ZEN-720019
Table 1.1 characters of GRP

Pipeline Inner Dia Thickness Outer Dia Lamination Thk Lamination Width
4 Lines 2600 29 2658 30.6 1250

1.4    Construction Period

Working period : 07th June,2022 ~ 23rd March, 2024.

2. GENERAL CONDITION AND METHOD STATEMENT

2.1    General Introduction

According to the preliminary design for the pipeline of CHEC, we propose to install 4×DN3000 RC pipe sleeve by pipe jacking method. And then install the DN2600 GRP in each pipe sleeve. The gap between pipe sleeve and GRP pipes will be filling up by cement grouting.

Layout of CW pipeline

Fig.2.1 Layout of CW pipeline

Typical Section of CW pipeline

Fig.2.2 Typical Section of CW pipeline

2.2    Ground Conditions

The locations of three boreholes (BH1, BH3, and BH4) in relation to the line of Drives A (Launch shaft )and B(Receiving Shaft) are shown in Fig.2.3. The ground conditions comprise cultivaded soil, sandy clay, brownish grey, whitish grey gravelly sand (≈3.9 m), poorly graded silty sand, well - graded silty sand, bluish grey, whitish grey, loose (≈4.7 m),clayof lowplasticity,clayof intermediate plasticity blackish grey, brownish grey, very soft to soft (≈2.4 m) and poorly graded silty sand, bluish grey, gray, medium dense (≈2.4 m).
From the summary stratigraphy in Fig. 2.4, it can be seen that the tunnel passes through the clay and silty sand layers. The water table was found to be at a depth of 3.5 m in a borehole close to the Launch shaft of Drive A to B.

Layout of Bore Holes

Fig.2.3 Layout of Bore Holes (from VA1)

Layout of Bore Holes (BH1 from VA1)

Fig.2.4 Layout of Bore Holes (BH1 from VA1)

2.3    Launch Shaft and Receiving Shaft

As per the preliminary design of CHEC, launch shaft and receiving shaft will be steel sheet pile with strut supporting structure.

Section of CW pipeline

Fig.2.5 Section of CW pipeline
Table 2.1 Contents of work

Method statement

Plan of Launch Shaft

Fig.2.6 Plan of Launch Shaft

Section of Launch Shaft

Fig.2.7 Section of Launch Shaft. Biện pháp thi công khoan ống HDD bằng tiếng anh.

2.4    Jacking Pipes

RCJP will be supplied by Hung Vuong Construction Company, which we have cooperated since 2003 during the project “Environment Development of Ho Chi Minh City, Nhieu Loc Thi Nghe Bason”. The technology of RCJP precast was supplied by CHEC.

3. CONSTRUCTION METHOD STATEMENT

3.1    Shaft construction

3.1.1 Construction sequence

Shaft Construction Sequence

Fig.3.1 Shaft Construction Sequence

3.1.2 Sheet pile construction

Plan of Launch Shaft

Fig.3.1 Plan of Launch Shaft

a. Preparation work

-    Approved all documents

-    Mobilization equipment and materials.

Sheet pile Larsen IV

Sheet pile Larsen IV    

Robot machine

Robot machine

b. Survey work
-    Use total station machine to setting up.

-    Marking point by paint on the site.
-    Checking underground utilities.

c. Sheet pile driving
-    Checking weather before construction

-     Welding sheet pile with length of design.

-     Use crane to lifting sheet pile for driving.
-    Sheet pile driving with checking alignment by water ruler.

Marking centre of line
Marking centre of line    

First sheet pile installation

First sheet pile installation

d. Cleaning after construction

-    Remove all materials and rubbish

-    Keep clean of site.
e. Construction sequence

Construction sequence

However, driving sheet piles with vibratory hammer also will be an alternative option if permitted.

3.1.3 Jet Grouting construction

a. General

+ Soil improvement is carried out at the bottom of shaft. The purpose of this work is protection and water proofing for the shaft bottom during construction work.
+ Jet grouting method is able to meet the above these requirements
+ The statement consists of site preparation, materials supply and installation.

Layout of Jet Grouting

Fig.3.2 Layout of Jet Grouting

b. Method statement of Jet grouting work

+ Jet Grouting column will be carried out adopted the operating parameters (such as Improved DIA, discharge flow, grouting pressure, Pulling up rate…) by experience.
+ JSG method is used High-pressure injection of cement slurry and air from double tube with rotation.

Schematic diagram of Jet grouting

Fig.3.3 Schematic diagram of Jet grouting

+ Material mixing:

+ The slurry shall be mixed continuously during the Jet grouting progress on site by the mixer. The slurry consumption will be calculated based on the fluid flow rate set up on the high pressure pump machine.

Mixing proportion per 1.0m3

No Materia  1 Unit Quantity
1 PCB40 KG

550

2 Water L

822

c. Operation parameters for Jet grouting

Operating parameters for Jet grouting

Operating parameters for Jet grouting

d. Sequence of Jet grouting work

+ Preparation work
The following activities will be conducted before starting works:
•    Utility services detection needs to be conducted thoroughly to check for any

existing services. If there are utility services affecting the work, the effected

services need to be duly exposed and well protected at the location of grouting to

avoid damage.

•    Access for equipment and man power will be made.

•    Transportation of material shall be done using truck and unloading by manual labour or crane as necessary.
•    Materials will be kept at designated locations with adequate protection.

•   Workers will be trained for safety and acknowledge of the correct sequencing of work execution.

Communication on Site will be conducted via mobile phones and walkie-talkies.

+ Setting - up Equipment and Machinery

•    Assemble the drilling machine on site.

•    Attach the drilling machine with necessary mixing equipment (such as rod, monitor and bit) for Jet Grouting.

•    Set up the cement mixing ratio as design parameters.

+ Drilling work

•    Check the verticality of the drilling machine using the water level ruler that is attached to the drilling machine and the plumb-lines method from two perpendicular directions
•    Check the nozzle that is used to inject the cement grout by visual inspection prior to the drilling works. A simple water test shall be conducted if necessary. The water test utilizes the injection of water into the rod tubes. If the water successfully emits from the nozzle, the nozzle is in good working condition.
•    Check the pressure of the pump by visual inspection of the dial pressure gauge.

•    Execute drilling of a small diameter bore-hole to the designated depth using low pressure water flushing from the bottom for the Jet grouting works.
•    Measure and record the designated depth manually from the balance rod above the ground level and compared with the actual of the rod.

+ Jet grouting work

•    After completing the drilling work, the operating mode will be switched from drilling mode to Jetting mode.
•    Jetting pressure will be increased to 20 ± 2 Mpa and then Jetting mode is set. •    Control the grouting pressure by the dial pressure gauge.
•    Record tip level by measure the length of drilling rod manually.

•    Inject cement grout with ultra - high - pressure pump through the nozzle screen when the drill rod is slowly withdrawn from the bore-hole.

•    The injection rate of grouting and withdraw rate will be decided base on operation parameter

•    The removal or uplifting by rotation of the drill rod is carried out at a rate of 10-12 rpm

•    Injection volume will record at a flow meter.

•    If it came to unexpected high pressure, safety valve of the pump is activated.

+ Cleaning and Slime/ Slurry Disposal
•    After completion of the grouting works, the equipment including rods and mixing plant shall be cleaned for the next position. All slime/ slurry is not allowed to spread over or outside of the work areas. To protect the spread of the slime, the pit shall 
be arranged near the working areas. The size of pit shall be determined to ensure that effluent cannot enter the public drainage system.
•    Sludge disposal be collected in pits and shall be disposed of site daily by dump 
trucks to the approved dumping area.

+ QUALITY CONTROL/ QUALITY ASSURANCE

+ Quality control before construction
Before construction, the Contractor shall take samples of materials and carry out necessary test for all materials proposed to be used.
Jet grouting equipment shall be functional properly such as rotating and moving after grouting rod according to the pre-determined supplying ratio of grout from the mixing machine with the pre-determined pressure and volume.
Pressure gauge and others shall be used to measure construction parameters, which are necessary to be adjusted before construction.

+ Quality control during construction phase

Quality control during construction is controlled as following: Quality control of Jet grouting
Method

Xem thêm: CONSTRUCTION MEASURES OF SURROUND DRILLING 04 CW DN2600 PIPELINES

 

CÔNG TY CP TƯ VẤN ĐẦU TƯ & THIẾT KẾ XÂY DỰNG MINH PHƯƠNG

Địa chỉ: Số 28B Mai Thị Lựu, Phường Đa Kao, Q.1, TPHCM

Hotline:  0903649782 - (028) 3514 6426

Email: nguyenthanhmp156@gmail.com

 


Tin tức liên quan

Horizontal Directional Drilling (HDD) Method Statement
Horizontal Directional Drilling (HDD) Method Statement

1222 Lượt xem

This document has been prepared to describe the methodology by which MCD/HDDT propose undertaking the site preparation, mobilization, drilling operations, pipe installation, pre-commissioning and reinstatement operations for the installation of the 6 HDD crossings on the Block B Omon Project - Onshore Pipeline.

Natural gas line installation
Natural gas line installation

1708 Lượt xem

With a simple natural gas line installation process, shorten the construction time, less impact on the environment and living activities of the residents around the construction area.

JUNCTION INSTALLATION SURFACE DRILLING ĐÀ RIVER
JUNCTION INSTALLATION SURFACE DRILLING ĐÀ RIVER

1277 Lượt xem

The underground drilling through and various obstacles by underground drilling technique is more and more widely used around the world.

Horizontal directional drilling technology
Horizontal directional drilling technology

1554 Lượt xem

All horizontal directional drilling job shall be performed in strict accordance with all governing federal, state, and local regulations. The horizontal directional drilling HDD operations shall be conducted in accordance with the latest approved editions of the following referenced documents where applicable:

Using directional drilling & underground technology instead of ditching
Using directional drilling & underground technology instead of ditching

1613 Lượt xem

Directional drilling & underground tech is a method of construction and installation of a new underground pipeline by putting the drill bit underground and using a large-capacity hydraulic jack to push the segments into the ground.

Drilling work to pull LNG pipes across the road for oil and gas companies in Ba Ria – Vung Tau
Drilling work to pull LNG pipes across the road for oil and gas companies in Ba Ria – Vung Tau

1336 Lượt xem

Here are a few pictures of the Drilling work to pull LNG pipes across the road for oil and gas companies in Ba Ria – Vung Tau:


Bình luận
  • Đánh giá của bạn
Đã thêm vào giỏ hàng