Thi công khoan ống ngầm nhà máy nhiệt điện

Thi công khoan ống ngầm nhà máy nhiệt điện. Vietnam Vung Ang Power Plant Phase II Pipe Jacking Project. Foundation Pit Engineering Calculation Book. Dịch vụ thi công khoan ngầm - Minh Phương Corp

Thi công khoan ống ngầm nhà máy nhiệt điện Vũng Áng 

Vietnam Vung Ang Power Plant Phase II Pipe Jacking Project. Foundation Pit Engineering Calculation Book. 

Kĩ thuật tính toán hố móng dự án khoan ống giai đoạn 2 cho nhà máy nhiệt điện Vũng Áng

Project name

Project No.

Calculator

Proofreader

Reviewer

Examiner

DateMay 29th , 2022

Specifications and Procedures

《Technical specification for building foundation pit supportJGJ 120-2012

Internal force calculation method

Incremental method

Support structure safety level

Level 1

Supporting Structure

Importance Coefficientγ0

1.00

Foundation pit depth(m)

14.630

Embedded depth (m)

4.370

Pile top elevation (m)

-1.000

Pile Material Type

Steel sheet Pile

├Cross-sectional area per linear meter A(cm2)

236.00

├Moment of inertia per linear meter I(cm4)

39600.00

└Flexural modulus per linear meter W(cm3)

2200.00

└Bending resistance f(MPa)

215

With or without crown beam

No

waterproof curtain

No

Grading series

1

Number of overloads

1

Horizontal concentrated force on support structure

0

 


[ Grading Information ]

Slope number

Table width (m)

Slope height (m)

Slope factor

1

0.500

1.000

1.000

 

[ Overload Information ]

 

Overload serial number

Type

Overload value

(kPa,kN/m)

Depth of action

(m)

Action width

(m)

Distance from pit

(m)

Form

Length

(m)

1

 

15.000

---

---

---

---

---

 

[ soil layer information ]

 

Soil layers

6

Reinforced soil in pit

No

Final inner dewatering depth

15.130

outside water depth (m)

0.000

Whether the inner water level changes with the excavation process

Yes

The distance between the inner

water level and the excavation surface (m)

1.000

Elasticity calculation method specified by soil layer

Elastic calculation method

m

Calculation method of earth pressure outside pit during internal force

calculation

initiative

 

[ soil layer parameters ]

 

layer number

Soil name

Layer thickness

(m)

Weig ht

(kN/m

3)

Float weight

(kN/m3)

Cohesion

(kPa)

Internal friction angle (degree)

Cohesion

underwater (kPa)

Internal friction angle underwater

(degree)

1

miscellaneous fill

4.30

18.0

8.0

6.00

8.00

6.00

8.00

2

fine sand

4.50

19.0

9.0

0.00

25.00

0.00

25.00

3

clay soil

0.90

20.9

10.9

7.50

20.20

7.50

20.20

4

clay soil

4.80

21.0

11.0

12.40

25.35

12.40

25.35

5

clay soil

3.90

25.0

15.0

11.70

25.46

11.70

25.46

6

medium

weathered rock

100.00

20.0

10.0

---

---

15.00

30.00

layer number

Frictional resistance with anchor (kPa)

Soil and water

calculation method

m,c,K value

Standard value of ultimate bearing capacity (kPa)

1

60.0

combine

m method

1.08

120.00

2

60.0

separate

m method

10.00

120.00

3

60.0

combine

m method

6.89

120.00

4

120.0

combine

m method

11.56

120.00

5

120.0

combine

m method

11.59

120.00

6

120.0

combine

m method

4.00

120.00

layer number

Effective internal friction angle φ'(degree)

Estimation formula of static earth pressure coefficient

static earth pressure coefficient Ko

1

---

---

---

2

---

---

---

3

---

---

---

4

---

---

---

5

---

---

---

6

---

---

---

 

anchor channels

6

reaming bolt

 

Anchor

No

Anchor type

horizontal spacing (m)

vertical spacing (m)

Incidence angle

(°)

Total length

(m)

Anchoring section length (m)

1

inner support

1.000

1.500

---

---

---

2

inner support

1.000

2.700

---

---

---

3

inner support

1.000

2.950

---

---

---

4

inner support

1.000

3.300

---

---

---

5

inner support

1.000

1.000

---

---

---

6

inner support

1.000

2.480

---

---

---

 

Anchor No

Pre Pressure (kN)

Anchor stiffness (MN/m)

Anchor diameter (mm)

Work condition No

Fixed anchor

Adjustment coefficient

Material resistance (kN)

Material resistance

Adjustment coefficient

1

0.00

9754.71

---

2

---

3000.00

1.00

2

0.00

9754.71

---

4

---

3000.00

1.00

3

0.00

9754.71

---

6

---

3000.00

1.00

4

0.00

9754.71

---

812

---

3000.00

1.00

5

0.00

7162.46

---

11

---

3000.00

1.00

6

0.00

2520.00

---

10

---

3000.00

1.00

 

[Earth pressure model and coefficient adjustment ]

Elastic Earth Pressure Model:                      Classical earth pressure model:

 

Layer No

Soil Name

Water and water

Water pressure

Adjustment coefficient

Outside earth pressure Adjustment

coefficient 1

Outside earth pressure Adjustment

coefficient 2

Inside earth pressure

Adjustment coefficient

Inside earth pressure

value(kPa)

1

miscellane ous fill

combine

---

1.000

1.000

1.000

10000.000

2

Fine sand

separate

1.000

1.000

1.000

1.000

10000.000

3

clay soil

combine

---

1.000

1.000

1.000

10000.000

4

clay soil

combine

---

1.000

1.000

1.000

10000.000

5

clay soil

combine

---

1.000

1.000

1.000

10000.000

6

medium weathered rock

combine

---

1.000

1.000

1.000

10000.000

 

[ Working condition news ]

Working condition

No

Working condition

type

depth

(m)

Anchor

No

1

excavate

2.000

---

2

add support

---

1.inner support

3

excavate

4.700

---

4

add support

---

2. inner support

5

excavate

7.650

---

6

add support

---

3. inner support

7

excavate

10.950

---

8

add support

---

4. inner support

9

excavate

14.630

---

10

add support

---

6. inner support

11

add support

---

5. inner support

12

dismantle

---

4. inner support

[Design Parameters ]

Overall stability calculation method

Swedish section law

Stability calculations using stress states

total stress method

Whether to consider internal support in stability calculation

Soil strip width in strip method (m)

1.00

Stiffness reduction factor K

0.850

Anti-bump stability considering arc sliding mode

Overturning stability by taking moment to support bottom

Overturning stability with the lowest anchor as the axis

[Design results ]

[Structural calculation]

Various working conditions

Various working conditions

Working condition 2 - Support

Báo giá khoan ngầm - Dịch vụ thi công khoan ống kích ngầm

 

Internal force displacement chart

Working condition 12 - Remove Support10.45m

envelope diagram

Envelope diagram




Subsidence map

[Section calculation ]

[Section parameters ]

Moment reduction factor

1.00

Shear reduction factor

1.00

Load Partial Factor

1.25

[Internal force value ]

Part

No

Internal force type

elastic method calculated

classical law

calculated

internal force design

value

internal force

practical value

Maximum bending moment inside the foundation pit (kN.m)

233.53

462.93

291.91

291.91

1

Maximum bending moment outside the foundation pit (kN.m)

213.27

465.51

266.59

266.59

Maximum shear force (kN)

267.85

254.29

334.81

334.81

 

See details: Pipe Jacking Project of Vietnam Vung Ang II power plant

 

CÔNG TY CP TƯ VẤN ĐẦU TƯ & THIẾT KẾ XÂY DỰNG MINH PHƯƠNG

Địa chỉ: Số 28B Mai Thị Lựu, Phường Đa Kao, Q.1, TPHCM

Hotline:  0903649782 - (028) 3514 6426

Email: nguyenthanhmp156@gmail.com

 


Tin tức liên quan

Biện pháp thi công khoan ngầm kéo cáp quang hiện đại
Biện pháp thi công khoan ngầm kéo cáp quang hiện đại

2415 Lượt xem

Có nhiều cách lắp đặt cáp điện, và cách đặt cáp cũng khác nhau, và dòng điện khả năng mang cũng khác nhau. Bây giờ chúng ta hãy giới thiệu các phương pháp đặt cáp điện là gì? Biện pháp thi công kéo cáp quang.

Tại sao doa lại quan trọng đối với công nghệ khoan ngầm và các loại máy doa có sẵn
Tại sao doa lại quan trọng đối với công nghệ khoan ngầm và các loại máy doa có sẵn

1709 Lượt xem

Khoan và doa nghe có vẻ giống nhau. Tuy nhiên, các từ không thể thay thế cho nhau. Trong khi một số dự án yêu cầu cả hai phương pháp để hoàn thành, chúng hoàn toàn là các nhiệm vụ khác nhau.

Thi công khoan kích ngầm kéo ống thép qua đường
Thi công khoan kích ngầm kéo ống thép qua đường

46 Lượt xem

Minh Phương đang thi công thực hiện dự án khoan kích ngầm kéo ống thép qua đường. Công trình kéo ống thép có chiều dài 28m qua đường Đồng Văn Cống - TP. Thủ Đức với kích thước ống thép DN400 với chiều sâu 4m5.

Có nên lựa chọn công nghệ khoan định hướng hay không? Đơn giá khoan ngầm bao nhiêu?
Có nên lựa chọn công nghệ khoan định hướng hay không? Đơn giá khoan ngầm bao nhiêu?

1352 Lượt xem

Mặc dù đây không phải là một nhiệm vụ phức tạp, nhưng việc phạm sai lầm có thể dẫn đến nhiều thiệt hại và do đó, bạn có thể gặp rắc rối. Vậy có nên lựa chọn công nghệ khoan định hướng hay không? Đơn giá khoan ngầm bao nhiêu? Chúng ta hãy cùng nhau tìm hiểu ngay sau đây:

Khoan ngầm qua sông kéo ống dẫn khí
Khoan ngầm qua sông kéo ống dẫn khí

1392 Lượt xem

Khoan ngầm qua sông kéo ống dẫn khí thuộc về công nghệ không rãnh, là những thủ tục mà mục đích là xây dựng, thay thế hoặc sửa chữa tất cả các loại đường ống đường kính nhỏ (cống rãnh, hệ thống dẫn nước, mạng điện, thông tin liên lạc, mạng khí đốt tự nhiên, trong số những người khác) mà không cần dùng đến các phương pháp cắt giảm lộ thiên.


Bình luận
  • Đánh giá của bạn
Đã thêm vào giỏ hàng